North America does not accept a CE mark as proof that a charger is safe to install. It accepts a listing, and for DC fast charging equipment that listing is UL.
This 800kW split-type system carries UL 2202-2022, the standard for EV charging system equipment, and UL 2231-2, the standard for the personnel protection system that guards the operator against electric shock. Both are printed on the nameplate, and both survive the authority having jurisdiction's inspection.
This page explains the two standards, the 480V North American input design, and the compliance points that keep projects out of rework.
We should be direct about what this page is not: it is not legal advice, and local codes vary by state and county. What it is, is the practical picture of how a listed 800kW system clears the hurdles we see most often in US and Canadian projects.

The difference between a CE mark and a UL listing is not paperwork. It is whether the equipment can legally be installed and insured.
CE is a self-declaration by the manufacturer; UL is a third-party listing backed by factory inspections and follow-up audits.
Most US jurisdictions, utilities, and insurers require a nationally recognized testing laboratory listing, which CE alone does not provide.
UL 2202-2022 covers the charging system equipment as a whole: enclosure, wiring, input circuits, and output circuits.
UL 2231-2 covers the personnel protection system, the safety interlock chain between the connector and the DC output.
With both listings, the 800kW system is ready for permitting without a custom engineering evaluation in most states.
For Canada, the same equipment can be evaluated against CSA counterparts; our UL files support that path.
|
Parameter |
Specification |
|
Model |
AF-DC-800-Series |
|
Rated Output Power |
800kW |
|
Cabinet Dimensions (mm) |
2200 × 1800 × 1000 |
|
Standard Terminal (mm) |
1517 × 650 × 300 (250A) |
|
Liquid-Cooled Terminal (mm) |
1630 × 600 × 500 (600A) |
|
Input Voltage |
AC480V±10%, 50/60Hz |
|
Output Voltage Range |
300-1000VDC constant power |
|
Charging Outlets |
2-16 guns |
|
Standards |
UL 2202-2022, UL 2231-2 |
|
Power Factor |
≥0.99 |
|
Noise Level |
≤65dB |
|
Protection Grade |
IP54 |
|
Operating Temperature |
-25°C ~ +50°C |
|
Warranty |
2 Years Standard |
Interstate corridor stations where a 480V three-phase service already exists and 800kW is the contracted capacity.
Truck stops and rest areas bidding on NEVI or state-funded programs that require listed equipment.
Corporate and fleet yards replacing diesel infrastructure with high-power DC charging.
Shopping and entertainment venues with large parking lots and a single dedicated transformer.
Utility pilot projects demonstrating high-power charging on the distribution network.
Airport and transit parking structures where a single 480V service feeds multiple charging zones.
The cabinet is designed around the North American commercial standard: AC480V ±10% at 50/60Hz three-phase input. No step-up transformer is needed between a standard 480V service and the cabinet; the rectifier stage converts directly to a 300-1000VDC bus.
Power factor correction holds the input at ≥0.99, which keeps the demand metering clean and avoids penalty charges on commercial tariffs that bill for reactive power.
The 800kW pool feeds 2 to 16 terminals. Each terminal negotiates its current with the controller, so a 600A liquid-cooled stall and a 250A air-cooled stall coexist on the same cabinet, and the output connectors follow the market: CCS1 for North America, with NACS available.
Ground-fault and personnel protection are handled inside the cabinet in line with UL 2231-2, and the station connects to OCPP 1.6 or 2.0 backends for load management and remote control.
Heat is managed by the cabinet's own cooling system, so the ≤65dB noise rating holds even at full output. That matters in commercial lots where a neighbor's property line sits close to the equipment pad.
Permitting is where listed equipment pays for itself. Three documents matter at inspection time, and we supply all of them.
The UL mark on the nameplate, matched to the model number in our listing file, is what the inspector photographs.
NEC Article 625 covers EV charging equipment installation; our installation manual maps the cabinet to its feeder, overcurrent, and disconnecting-means requirements.
NFPA 70 is the code itself, and Article 625 sits inside it; AHJ review focuses on grounding, bonding, and the disconnect within sight.
We provide the UL test reports and the certificate of conformity for the specific serial ranges shipped.
The input-side documentation includes the 480V wiring diagram and torque schedules for the service connection.
For funded projects, our UL documentation matches the equipment lists that NEVI and state programs require from bidders.
Step 1. Enclosures are punched and laser-cut from steel coils, then robot-welded on FANUC lines.
Step 2. TRUMPF press brakes form the panels; powder coating and curing follow.
Step 3. AC distribution is wired on the AC line with UL-recognized components and torque-controlled terminations.
Step 4. Rectifier modules and the personnel protection board are fitted on the DC line.
Step 5. Each cabinet is load-tested to 800kW with power factor, ripple, and protection checks recorded.
Step 6. A 48-hour burn-in cycles the unit; logs are bound to the serial number.
Step 7. UL follow-up inspection samples are drawn from production per the listing program.
Step 8. Final inspection and crating; the plant shipped over one million units cumulatively through 2024.
Choose the 800kW UL-listed system when your project is in the United States or Canada, when a funder or utility requires listed equipment, or when your AHJ will not accept CE-only hardware. It is also the right call when you want one model that covers growth from 2 to 16 guns.
Do not choose it for a single 2-gun retail corner in a market without UL enforcement; the listing carries a cost, and a CE-only unit will do the job there.
Check your service capacity before ordering: the cabinet needs a real 800kW at the 480V service, plus room for inrush and metering. We send a site-data checklist with the quotation, and our engineers review it before you commit.
Lead times also differ from CE-only markets: UL-listed production runs follow the same 15-20 working day schedule, but some US projects need the listing documents early for funding applications. Ask for the documentation pack when you request pricing, not after you win the bid.
And if your project is purely speculative, with no site, no utility agreement, and no permit path yet, wait before ordering. The equipment keeps; the parking lot might not.
UL 2202-2022 and UL 2231-2 are listed, with factory follow-up audits already in place.
15-20 working days delivery after drawing approval; MOQ from one container.
OEM/ODM: North American branding, NACS or CCS1 connector sets, and custom cable lengths.
Documentation package for brokers and AHJs: UL reports, certificates of origin, and wiring diagrams.
A Yueqing-headquartered manufacturer founded in 2014, exporting to 40+ countries including the US and Canada.
The cabinet ships in a steel-framed crate at roughly 2300 x 1900 x 1150 mm with four lifting points; terminals are palletized with cables coiled and connectors protected. A 40ft high-cube container fits the cabinet plus up to eight terminals.
Delivery terms are FOB Ningbo or CIF to a US or Canadian port. Documents, invoice, packing list, bill of lading, UL test reports, and certificate of origin, are issued within 3 working days of loading.
The crate includes a rigging diagram for the 2200mm-tall cabinet, and our commissioning guide covers the forklift and crane options for the site.
Two-year standard warranty covers the cabinet, terminals, power modules, and the protection controller.
Cross-ship exchange on warranty failures; replacement dispatch within 5 working days from our stock.
Remote OCPP diagnostics and firmware updates handled by our engineers across time zones.
Spare-part kits for North American customers: fuses, connectors, and control boards kept on the shelf.
Annual maintenance advice includes torque rechecks after the first year and a connector wear inspection every 6 months.
Wrong: feeding the cabinet from a 208V service. Right: provide AC480V ±10% three-phase, as the UL listing assumes.
Wrong: omitting the disconnecting means within sight of the equipment. Right: install the disconnect per NEC 625 and our wiring diagram.
Wrong: grounding through the conduit alone. Right: run a dedicated equipment grounding conductor per the installation manual.
Wrong: assuming the UL listing covers an unlisted third-party terminal. Right: use the terminals supplied with the listed system.
Wrong: skipping the AHJ walkthrough before energizing. Right: invite the inspector with the UL file and test reports in hand.
A charging network in California, United States commissioned two 800kW cabinets at a corridor site and passed inspection on the first visit. The project manager's only complaint: the crate arrived two days later than the trucking quote, which pushed commissioning to a weekend.
A utility contractor in Ontario, Canada used the 480V wiring diagrams to pre-bid the electrical work. His feedback was that the torque schedule saved him a rework call, though he wished the terminal cable were 0.5m longer for his stall layout.
A fleet operator in Ohio, United States runs 10 guns per cabinet for its truck yard. After nine months, one terminal's connector latch needed replacement; the cross-ship spare arrived in four days, and the rest of the station never stopped charging.
A: Listed, under UL 2202-2022 and UL 2231-2, with ongoing factory follow-up audits.
A: US permitting and insurance generally require a nationally recognized testing laboratory listing; CE is a manufacturer's self-declaration.
A: AC480V ±10% at 50/60Hz, the standard North American commercial service.
A: Proper feeder sizing, overcurrent protection, and a disconnecting means within sight; our manual maps each requirement.
A: Yes, connector sets are assigned per terminal at order time.
A: Only if your service is medium voltage; from a 480V service the cabinet connects directly.
A: From 2 to 16, mixing 250A air-cooled and 600A liquid-cooled terminals.
A: UL test reports, certificate of origin, packing list, and the wiring diagram, all included with the shipment.
Address
No. 237, Weisan Road, Yueqing, Zhejiang, China
Tel
Talk Directly to Our EV Charger Factory
Get factory-direct pricing, custom solutions, and expert support.
- Fast Response – Reply within 24 hours.
- OEM/ODM – Flexible customization and sample orders.
- Certified Quality – CE, TÜV, CB, and CCC options.
- Custom Quotes – Tailored to your specifications.
- Technical Support – Expert help with OCPP, DLB, and system integration.